The BFI Plant consists of an Ammonia Plant, Urea Synthesis and Granulation Plants, Offsite & Utilities Plant and a dedicated export jetty, the BFI Terminal (BFIT).

The BFI Plant is primarily focused on the production and export of Granular Urea. With a main feedstock of natural gas and raw water both sourced domestically, the BFI Plant has a production nameplate capacity of 2,200 metric tonnes per day of ammonia which is fully converted to produce 3,900 metric tonnes per day of granular urea.

By the numbers

Ammonia per day
Ammonia per day
0 MTPD
Urea per year
Urea per year
0 MT
seed
Bags packed via in-house packing facility
0 KG

Quick facts

Parts

Ammonia Plant

Ammonia Plant

Urea Synthesis & Granulation Plant

Urea Synthesis & Granulation Plant

BFI Terminal (BFIT)

BFI Terminal (BFIT)

Offsite & Utilities Plant

Offsite & Utilities Plant

Engineering, Procurement & Construction

Thyssenkrupp Industrial Solutions (tkIS), Germany

Licensors

Ammonia Process

Ammonia Process

Uhde Thyssenkrupp Industrial Solutions, Germany

Urea Process

Urea Process

Stamicarbon, The Netherlands

Granulation

Granulation

Thyssenkrupp Fertilizer Technologies, Germany

CAPACITY

2,200 MTPD Ammonia

2,200 MTPD Ammonia

converted into

Granular Urea

3,900 MTPD Granular Urea

Main feedstocK

Natural Gas

Natural Gas

Raw Water

Raw Water

EXPORT FACILITIES

BFI Terminal (BFIT)

BFI Terminal (BFIT)

BFI Terminal (BFIT)

Muara Port

Milestones

2013
2018
2021
2022
2023
2024
2025

October 2013

Incorporation of BFI

May 2018

Construction began by EPC Contractor.

December 2021

First production of Ammonia as feedstock.

2022

First production of Urea, as well as first shipments from BFI Terminal and Muara Port and partial takeover from EPC Contractor.

2023

BFI United

Started Operational Excellence journey, Code of Conduct, Safety Walkabouts, CARe Cards and ISPS Awareness. 1 million tonnes of Urea are produced and sold.

2024

Final takeover of plant, moving towards lean organisation. Achieved one year without Loss Time Incident and 2 million safe working hours. Also completed ISO 45001 Certification.

1st April 2025

Awarded IFA Industry Stewardship Champion (ISC).

2013
2018
2021
2022
2023
2024
2025

October 2013

Incorporation of BFI

May 2018

Construction began by EPC Contractor.

December 2021

First production of Ammonia as feedstock.

2022

First production of Urea, as well as first shipments from BFI Terminal and Muara Port and partial takeover from EPC Contractor.

2023

BFI United

Started Operational Excellence journey, Code of Conduct, Safety Walkabouts, CARe Cards and ISPS Awareness. 1 million tonnes of Urea are produced and sold.

2024

Final takeover of plant, moving towards lean organization. Achieved one year without Loss Time Incident and 2 million safe working hours. Also completed ISO 45001 Certification.

1st April 2025

Awarded IFA Industry Stewardship Champion (ISC).

Diversifying downstream opportunities.

Ethics and safety are the core tenet of working at BFI. Guided by merit and equal opportunity, we strive to create continuous value for customers and consumers, all while being responsible towards the environment.

BFI LOGO